ND Commits $500M to WBI Energy's Bakken East Gas Pipeline - Bakken Wire
Pipeline & Infrastructure

ND Commits $500M to WBI Energy's Bakken East Gas Pipeline

State Industrial Commission finalizes financial backstop for project to move 1 Bcf/d from McKenzie County to eastern ND by 2030.

Bakken Wire Staff·🔆Midday Wire·

The North Dakota Industrial Commission has unanimously voted to commit up to $500 million in state funding to WBI Energy’s planned Bakken East natural gas pipeline, according to the North Dakota Monitor. Tuesday's vote finalizes a financial backstop for the project, which was selected over a competing applicant last summer.

The Bakken East pipeline is designed to move 1 billion cubic feet of natural gas per day from McKenzie County in the heart of the Bakken to central and eastern North Dakota. WBI Energy, a subsidiary of MDU Resources, expects to bring the pipeline online by the end of 2030.

Gov. Kelly Armstrong, chair of the three-member Industrial Commission, said the commission is excited the project is moving forward. “The goal of the Legislature was both financial incentive and promotional incentive. I think both of those things are occurring,” Armstrong said, according to the Monitor. “This is going to be great in the short term, and it’s going to be great for the long term for North Dakota.”

The 2025 Legislature authorized the up to $500 million financing package, which is being provided through the state purchasing a portion of the pipeline’s transport capacity. The Industrial Commission also includes Agriculture Commissioner Doug Goehring and Attorney General Drew Wrigley.

Justin Kringstad, executive director of the North Dakota Pipeline Authority, received authorization to execute the agreement. He noted that after a closed-door briefing last month on the status of negotiations with potential shippers and customers, the need for state support remained. “Those details were revealed, and the need remained for that $50 million per year from the state side to continue advancing this forward,” Kringstad said, according to the Monitor source.

The commitment provides a critical financial guarantee for infrastructure aimed at moving more Bakken natural gas to in-state markets. This helps address the region's gas capture challenges and provides a stable outlet for producers. The project moved forward after a formal process earlier this year where potential gas shippers and customers, such as power plants or large industrial users, could express interest.

The pipeline represents a major state-backed investment in midstream infrastructure to support the long-term viability of the Bakken oil field. By creating a dedicated route for gas to eastern North Dakota, the project aims to add value to a resource that has often been constrained by pipeline capacity.

Source

North Dakota Monitor (Bing News)

pipelinenatural gasinfrastructurewbi energymdu resourcesnorth dakota industrial commissionbakken eastmckenzie county

Share this article

Related Articles

Pipeline & Infrastructure

Pipeline Outage Forces Bakken Producers to Rely on Trucking

North Dakota oil producers are moving crude by truck as a prolonged outage of an Enbridge Inc. pipeline in the state forces them to seek alternatives to avoid shutting in production, according to a Seeking Alpha report. The disruption is creating logistical challenges and increased costs for Bakken operators who typically rely on pipeline networks for efficient transportation to market. While the specific Enbridge line affected was not named in the report, such outages directly impact the takeaway capacity critical to the region's oil fields. "Some producers and marketers are trucking out production to delivery points," the report stated, highlighting the immediate industry response to maintain crude flow. Trucking is a more expensive and less efficient transport method compared to pipelines, squeezing operator margins. The continued outage underscores the vulnerability of regional production to infrastructure disruptions. For Bakken operators, the inability to access a major pipeline necessitates rapid adjustments in...

☀️Morning Wire·Nov 22
Bakken Producers Turn to Trucks Amid Enbridge Pipeline Outage - Bakken Wire
Pipeline & Infrastructure

Bakken Producers Turn to Trucks Amid Enbridge Pipeline Outage

North Dakota oil producers are moving crude by truck as a prolonged outage of Enbridge Inc.'s pipeline in the state continues, according to a Seeking Alpha report. The disruption is forcing operators to seek alternative transportation to avoid shutting in production. "Some producers and marketers are trucking out production to delivery points," the report stated. This shift to trucking represents a significant logistical and economic change for Bakken operators, who typically rely on pipelines for cost-effective transport. The increased reliance on trucking comes with higher costs and logistical challenges compared to pipeline shipments. For Bakken operators and royalty owners, these added expenses can compress margins and complicate daily operations. The ongoing outage highlights the critical nature of pipeline infrastructure for the Williston Basin's oil economy. Pipeline capacity is essential for maintaining steady, economical crude transportation from the wellhead to market. While the specific cause and expected duration of the Enbridge...

🔆Midday Wire·Nov 21
Pipeline & Infrastructure

Enbridge Pipeline Outage Forces Bakken Producers to Truck Crude

North Dakota oil producers are turning to trucks to move crude to market as a continued outage on a key Enbridge pipeline system restricts flows, according to a Bloomberg report cited by Seeking Alpha. The disruption is forcing operators to find alternative transport methods to avoid shutting in production. The shift to trucking represents a significant operational and economic challenge for Bakken producers. Pipeline transport is typically the most cost-effective and efficient method for moving large volumes of crude from the wellhead to refineries and hubs. Relying on trucks increases transportation costs per barrel and introduces logistical complexities. For operators in the Bakken formation, North Dakota's primary oil-producing region, prolonged pipeline constraints can directly impact cash flow and drilling plans. While trucking provides a necessary outlet to keep wells online, sustained use at scale can erode profit margins, especially if the outage continues indefinitely. The specific Enbridge pipeline involved and...

🌅Afternoon Wire·Nov 20