North Dakota Commits $500M to WBI Energy's Bakken East Gas Pipeline - Bakken Wire
Pipeline & Infrastructure

North Dakota Commits $500M to WBI Energy's Bakken East Gas Pipeline

The state Industrial Commission's final approval provides a financial backstop for the 1 Bcf/day project aimed at moving gas east by 2030.

Bakken Wire Staff·🌅Afternoon Wire·

The North Dakota Industrial Commission voted unanimously Tuesday to commit up to $500 million in state financing to WBI Energy's planned Bakken East natural gas pipeline, according to the North Dakota Monitor. The vote finalizes a state-backed financial guarantee for the project, which is designed to move 1 billion cubic feet of natural gas per day from the core of the Bakken oil field to eastern North Dakota.

Gov. Kelly Armstrong, who chairs the three-member commission, said the move fulfills the legislature's goals. "The goal of the Legislature was both financial incentive and promotional incentive. I think both of those things are occurring," Armstrong said. "This is going to be great in the short term, and it’s going to be great for the long term for North Dakota." The commission also includes Agriculture Commissioner Doug Goehring and Attorney General Drew Wrigley.

The commitment provides a financial backstop for the pipeline, a subsidiary of MDU Resources, with the state financing provided through the purchase of a portion of the pipeline's transport capacity. The 2025 Legislature authorized the $500 million for a pipeline to connect the western oil fields to the eastern part of the state, and the Industrial Commission selected WBI Energy's two-phase project for the guarantee last summer.

Justin Kringstad, executive director of the North Dakota Pipeline Authority, said details discussed in a closed-door session last month confirmed the continued need for state support. "Those details were revealed, and the need remained for that $50 million per year from the state side to continue advancing this forward," Kringstad said. He received authorization to execute the final agreement with WBI Energy on Tuesday.

The Bakken East pipeline is central to the state's strategy to better utilize natural gas produced alongside oil in the Bakken formation. WBI Energy expects to bring the pipeline online by the end of 2030. The company has been negotiating with potential shippers and customers, such as power plants or large industrial users, who expressed interest in the project during a formal process earlier this year.

The approval comes as North Dakota marks 75 years since the discovery of oil near Tioga on April 4, 1951, which launched the state's modern energy industry, according to AOL News. The state's commitment to major pipeline infrastructure underscores the continued central role of midstream development in supporting Bakken output and economic growth for decades to come.

For Bakken operators, the project promises a crucial new outlet for natural gas, helping to reduce flaring and capture more value from production. The state's direct financial involvement de-risks the large-scale infrastructure needed to move resources to new markets within North Dakota.

Source

North Dakota Monitor, AOL News

pipelinenatural gaswbi energymdu resourcesnorth dakota industrial commissionbakkeninfrastructurefinancing

Share this article

Related Articles

Pipeline & Infrastructure

Pipeline Outage Forces Bakken Producers to Rely on Trucking

North Dakota oil producers are moving crude by truck as a prolonged outage of an Enbridge Inc. pipeline in the state forces them to seek alternatives to avoid shutting in production, according to a Seeking Alpha report. The disruption is creating logistical challenges and increased costs for Bakken operators who typically rely on pipeline networks for efficient transportation to market. While the specific Enbridge line affected was not named in the report, such outages directly impact the takeaway capacity critical to the region's oil fields. "Some producers and marketers are trucking out production to delivery points," the report stated, highlighting the immediate industry response to maintain crude flow. Trucking is a more expensive and less efficient transport method compared to pipelines, squeezing operator margins. The continued outage underscores the vulnerability of regional production to infrastructure disruptions. For Bakken operators, the inability to access a major pipeline necessitates rapid adjustments in...

☀️Morning Wire·Nov 22
Bakken Producers Turn to Trucks Amid Enbridge Pipeline Outage - Bakken Wire
Pipeline & Infrastructure

Bakken Producers Turn to Trucks Amid Enbridge Pipeline Outage

North Dakota oil producers are moving crude by truck as a prolonged outage of Enbridge Inc.'s pipeline in the state continues, according to a Seeking Alpha report. The disruption is forcing operators to seek alternative transportation to avoid shutting in production. "Some producers and marketers are trucking out production to delivery points," the report stated. This shift to trucking represents a significant logistical and economic change for Bakken operators, who typically rely on pipelines for cost-effective transport. The increased reliance on trucking comes with higher costs and logistical challenges compared to pipeline shipments. For Bakken operators and royalty owners, these added expenses can compress margins and complicate daily operations. The ongoing outage highlights the critical nature of pipeline infrastructure for the Williston Basin's oil economy. Pipeline capacity is essential for maintaining steady, economical crude transportation from the wellhead to market. While the specific cause and expected duration of the Enbridge...

🔆Midday Wire·Nov 21
Pipeline & Infrastructure

Enbridge Pipeline Outage Forces Bakken Producers to Truck Crude

North Dakota oil producers are turning to trucks to move crude to market as a continued outage on a key Enbridge pipeline system restricts flows, according to a Bloomberg report cited by Seeking Alpha. The disruption is forcing operators to find alternative transport methods to avoid shutting in production. The shift to trucking represents a significant operational and economic challenge for Bakken producers. Pipeline transport is typically the most cost-effective and efficient method for moving large volumes of crude from the wellhead to refineries and hubs. Relying on trucks increases transportation costs per barrel and introduces logistical complexities. For operators in the Bakken formation, North Dakota's primary oil-producing region, prolonged pipeline constraints can directly impact cash flow and drilling plans. While trucking provides a necessary outlet to keep wells online, sustained use at scale can erode profit margins, especially if the outage continues indefinitely. The specific Enbridge pipeline involved and...